Special noise licence for works in Portugal
To work outside the permitted hours you need a special noise licence (licença especial de ruído) from the municipality, requested at least 15 working days before the works start (Regulamento Geral do Ruído, art. 15.º).
- Law
- Regulamento Geral do Ruído (approved by Decreto-Lei n.º 9/2007)
- Article
- 15.º
- Who issues it
- The municipality (câmara municipal), in exceptional and duly justified cases (n.º 1)
- Deadline
- Apply at least 15 working days before the works start (n.º 2)
- The request must give
- The exact location, start and end dates, hours, the reasons for working then, and noise-reduction measures where they apply (n.º 2)
- With the building permit
- If requested before or with the works application, the noise licence is issued on the same date as the permit (n.º 3 and 4)
- Limits
- For a licence longer than one month: 60 dB(A) in the evening and 55 dB(A) at night at nearby homes and other sensitive receptors (n.º 5)
- Official text
- pgdlisboa.pt/leis/lei_mostra_articulado.php?nid=1210&tabe...
- Sources
- pgdlisboa.pt/leis/lei_mostra_articulado.php?nid=1210&tabe...
- Checked
- 2026-11-05
Please note
- This page is a summary of the rule, not legal advice, and a court or a lawyer decides any dispute.